NPU-S ATLDOT Project Updates

From the Atlanta Office of Transportation (ATLDOT)

Good Evening, NPU Stakeholders:
Attached is the latest NPU-S Project Dashboard report (PDF) with the best available information on ATLDOT projects within your boundaries. In addition, here’s a quick status update on projects in design and construction:

Campbellton Rd - Smart Transit Corridor

GDOT is managing project bidding, contracting and construction. The concept design has been approved by GDOT. Surveying for entire street is currently underway.

Cascade Ave. Phase II Streetscape Project

This is part of the design-only Phase II of the Cascade Road/Ave Complete Street project

Cascade Rd - Complete Street

The design for Phase I is complete. Utility relocation work to improve power service in the corridor is underway. The construction bid package has been submitted to Office of Procurement. Right-of-way parcel acquisitions and closings are ongoing. However, rate of closings has been adversely affected by COVID-19. The project is currently on schedule for target construction start date of December 2020.

Cascade Rd - Resurfacing Phase 2

This work is being completed as part of the Cascade Road Complete Street project, with a target construction start date of December 2020.

Cascade Rd (TCC)

This work is being completed as part of the Cascade Road Complete Street project, with a target construction start date of December 2020.

Cascade Rd. Phase I Streetscape Project

This work is being completed as part of the Cascade Road Complete Street project, with a target construction start date of December 2020.

Avon Ave @ Westmont Rd & Orlando St

This intersection is included in a package of citywide signal upgrades and intersection improvements.  Final plans for the package are complete, utility evaluations are under way and bid package is being prepared for submission to the Office of Procurement.

Lee St. @ White Oak Avenue

This intersection is included in a package of citywide signal upgrades and intersection improvements.  Final plans for the package are complete, utility evaluations are under way and bid package is being prepared for submission to the Office of Procurement.

Neighborhood Sidewalk & ADA Improvements

Original scope is complete; however additional work been added to the contract that will be completed this summer.

Beecher St Resurfacing

This work is complete but will be designated as under construction until all punch list items on the contract are completed.

Stanton Road Resurfacing

This work is complete but will be designated as under construction until all punch list items on the contract are completed.

Right of Way Acquisition and Install Lighting (Atlanta  Beltine)

67.5% of total funding allotment has been paid; annual payments will continue until funding commitment is complete.

Campbellton Rd - Phase 2 (TCC)

Construction is complete, and punch list is underway. The final inspection expected this summer.

Campbellton Rd @ Oakland Ave

Construction is complete and punch list is underway. The final inspection expected this summer.

Signal Optimization and Detection Phase I

Most work completed on this citywide contract; will cover signal tech and traffic engineering work needed for Dekalb Ave Safety Improvements.

Smart Signal Systems Phase I

Most work completed on this citywide contract; will cover signal tech and traffic engineering work needed for Dekalb Ave Safety Improvements.


Please feel free to submit any questions regarding the projects listed in the monthly report to ATLDOT@atlantaga.gov. For updates on projects in construction, you may contact Adrian Carver, Construction Outreach Liaison, via email at: renewatl-acarver@atlantaga.gov or by phone at: 470-352-5427.