Atlanta DOT Monthly Project Dashboard Report

From the Atlanta DOT, here's a quick status update on projects in design and construction in NPU-S:

Campbellton Rd - Smart Transit Corridor

GDOT is managing project bidding, contracting and construction. The concept design has been approved by GDOT. Surveying for entire street is currently underway.

Cascade Ave. Phase II Streetscape Project

This is part of the design-only Phase II of the Cascade Road/Ave Complete Street project.

Cascade Rd - Complete Street

The design for Phase I is complete. Utility relocation work to improve power service in the corridor is underway. Right-of-way parcel acquisitions and closings are ongoing. The project has been resubmitted to the Office of Procurement for re-bid. Target construction start date has been revised to Spring 2021.

Cascade Rd - Resurfacing Phase 2

This work is being completed as part of the Cascade Road Complete Street project, with a target construction start date of Spring 2021.

Cascade Rd (TCC)

This work is being completed as part of the Cascade Road Complete Street project, with a target construction start date of Spring 2021.

Cascade Rd. Phase I Streetscape Project

This work is being completed as part of the Cascade Road Complete Street project, with a target construction start date of Spring 2021.

Avon Ave @ Westmont Rd & Orlando St

This intersection is included in a package of citywide signal upgrades and intersection improvements. Final plans for the package are complete and bid package has been submitted to the Office of Procurement.

Lee St. @ White Oak Avenue

This intersection is included in a package of citywide signal upgrades and intersection improvements. Final plans for the package are complete and bid package has been submitted to the Office of Procurement.

Neighborhood Sidewalk & ADA Improvements

Complete

Right of Way Acquisition and Install Lighting (Atlanta Beltline)

67.5% of total funding allotment has been paid; annual payments will continue until funding commitment is complete.

Campbellton Rd - Phase 2 (TCC)

Complete

Campbellton Rd @ Oakland Ave

Complete

MARTA Offset - Sidewalks

Two (2) design packages for citywide sidewalk and ADA installations are complete and a third design package is in progress. Atlanta City Council has approved ROW legislation so acquisition activities can proceed.

Signal Optimization and Detection Phase I

Most work completed on this citywide contract; will cover signal tech and traffic engineering work needed for Dekalb Ave Safety Improvements.

Smart Signal Systems Phase I

Most work completed on this citywide contract; will cover signal tech and traffic engineering work needed for Dekalb Ave Safety Improvements.

Please feel free to submit any questions regarding the projects listed in the monthly report to ATLDOT@atlantaga.gov.

For updates on projects in construction, you may contact:

Adrian Carver,
Construction Outreach Liaison,
renewatl-acarver@atlantaga.gov
470-352-5427.

No comments: